Skip to main content
Level 3
March 25, 2022
Question

Client Letter

  • March 25, 2022
  • 1 reply
  • 10 views

How do we get the due date on the client letter for partnerships on extension to reflect September 15th ? The letter is still reflecting March 15th

This topic has been closed for replies.

1 reply

abctax55
Level 15
March 25, 2022

In the extension screen (Screen 6), make sure the box for "print extension" ahs a "1" in it, AND the the box for e-file extension is checked.  I think they both have to be entered (even if you didn't efile the extension).  

HumanKind... Be Both
jra1Author
Level 3
March 25, 2022

We have a "1" in the print extension box and the e-file extension "checked" and the due date is March 15th on the letter.  I am wondering if we have something marked that is not allowing the program to change the date?  

So frustrating

 

abctax55
Level 15
March 25, 2022

All partnerships or just one?

Have you closed the program then restarted it (often resets things..)

HumanKind... Be Both